Remediation Update – September 13, 2024

House Street Update

Work continues at the House Street site as we continue implementing the EGLE-approved Work Plan for the construction of 27 acres of engineered caps.  As explained below, this work is still on track to be completed by the end of November.

The storms in late June and early July caused our contractor, RECON, to adjust onsite efforts when they couldn’t install liners due to the wet conditions.  They were able to begin work on the final detention basin and begin grading the areas around the mounds on the northern portion of the site.  These adjustments due to weather changed the timing of topsoil placement and seeding, but we anticipate work to remain on schedule.

During July, the remaining five landfill gas vents were installed on the southeast mound and final grading was completed on the northeast and southwest mounds.  Liners were then placed on the northeast, northwest, and southwest mounds in mid-July. 

View from Southwest Corner toward Northeast Corner of Site, 7/19/2024. Liner placed on Northwest and Northeast Mounds and being placed in the northern portion of Southwest Mound.

During the latter half of July, grading continued on the southeast mound to prepare it for liner placement, which took place in early August.

View from middle of Southeast Mound facing south toward site trailers (left side of photo) and House Street (along tree line).

During liner placement, each panel, seam, and patch was labeled (see white marking in photo above) and documented.  On-site testing was completed to confirm that all seams and patches meet the project specifications.  Samples of the seams are then sent off-site to an independent laboratory for testing to confirm that the seams meet the specifications before the barrier soil is placed over the liner.

Barrier soil placement.  A road is constructed across the edge of the mount where trucks can dump the sand that is to be placed on the liner.  The soil is then pushed onto the mound in 1-foot thick lifts and topsoil will be placed on top.

RECON expects to complete barrier soil installation by mid-September, with some areas already completed. Placement of topsoil and the mound seeding may begin as early as later this week.  During this phase topsoil will be brought in for placement and there will be some increased truck traffic.     

Final retention basin and access road construction will continue through the fall with sitework expected to be complete by the end of November.  In the spring any final seeding outside of the mound areas will be completed, and silt fence, job trailers, and remaining supplies will be removed.

We continue to conduct perimeter air monitoring, and there have been no exceedances of action levels.  The air monitoring data is available in the “Documents” section of this blog or by clicking on this link.  We continue to evaluate the data to be proactive with dust control as needed. 

Sunrise over Southeast Mound.

Tannery Update

Wolverine’s lead contractor Sevenson Environmental Services continues to construct the groundwater capture system per the EGLE-approved Response Activity Plan.

In July, the trenching subcontractor completed the installation of the nine groundwater interceptor trenches that are part of the system. The soil generated from installing these trenches was delivered to an approved Michigan landfill for appropriate disposal.

After completion of the trenches, a series of piezometers and groundwater extraction wells were installed will operate in conjunction with the trenches to monitor groundwater elevations and supplement the capture of groundwater for treatment.

After that the outfall discharge pipe to the Rogue River was constructed, using a temporary cofferdam around the work area to allow the excavation below the water line.  Horizontal direction drilling beneath Rum Creek was also completed in accordance with approved permits, to connect the utilities on either side of the creek and allow for captured groundwater to be transported from the south to the north side of the creek for treatment.

Current work consists of installing the remainder of the utility trenches that will connect the piezometers, groundwater extraction wells, and groundwater collection trenches to three kiosk buildings and subsurface control vaults that will serve to operate and monitor the interceptor system. This work began at the beginning of August and is ongoing.

We continue to conduct air monitoring at the perimeter of the project Site, and there have been no exceedances of action levels to date during site activities.  The air monitoring data is available in the “Documents” section of this blog or by clicking on this link.  We continue to monitor and evaluate the data to be proactive with dust control as needed. 

Photos of the site showing the installation of portions of the system are below:

A construction site with a white truck and a white tarp

Description automatically generated with medium confidence

Aerial view from the drone showing the installation of a piezometer on the north side of Rum Creek.

A construction site with a body of water and cars

Description automatically generated

Aerial view from the drone showing the installation of the cofferdam and the outfall discharge pipe, north side of Rum Creek.

We will continue to use this blog to keep the community informed as our investigation and related work progresses in the weeks and months ahead.  As always, residents with questions or feedback are encouraged to contact Wolverine Worldwide directly at HouseStreet@wwwinc.com or (616) 866-5627.

Remediation Update – July 3, 2024

House Street Remediation

Work continues at our House Street property as we continue implementing the EGLE-approved Work Plan to construct three engineered caps that will cover approximately 27 acres.  RECON, our contractor, has continued to excavate waste material and is grading the site to design elevations in the areas that will be below the caps.

During June, RECON installed sixteen landfill gas vents and six piezometers on the southwest, northwest, and northeast mounds.

Last week, the liner installer (ALCO) mobilized to the property and began installing liner on the northwest mound.  As the liner is placed, they weld the seams together using a heating tool.  ALCO tests samples of the seams onsite, and both RECON and GZA send samples of the seams to independent laboratories to confirm that they meet strength requirements.  Once the lab data is back and confirmed to be acceptable, the liner is covered with barrier soil, topsoil, and seed.

ALCO will return to the site after the July 4th holiday and continue installing liner in the northern mound areas, then will move to the southwest mound followed by the southeast mound.  We expect they will complete the liner installation by the end of July with topsoil placement and seeding finished in August.

We continue to collect perimeter air monitoring, and there have been no exceedances of action levels.  The air monitoring data is available in the “Documents” section of this blog or by clicking on this link.  We continue to evaluate the data to be proactive with dust control as needed. 

Photos of the site showing the grading and site preparation are below:

RECON excavating soil.

View of Northwest Mound facing west from the Northeast Mound.  The Mounds and the area between them are in the process of being graded and the anchor trench is being installed around the perimeter of the Northwest Mound in preparation for liner installation.

Rolls of liner staged onsite prior to placement.

ALCO beginning liner placement on the northwest mound.  The liner is placed in sheets that are then welded together using a heating tool.  The liner is weighted down with sandbags to hold it in place while the seam samples are being tested at the laboratory.

GZA field engineer observing ALCO’s liner seam field testing on the site.

Excavator removing soil along the northern side of the southeast mound while another operator grades material within the Southeast Mound footprint.

We still anticipate work this year will continue through November and that some remaining work, including grass planting outside of the mound areas, will occur in 2025. 

Tannery Remediation

Over the past several weeks Wolverine’s lead contractor, Sevenson Environmental Services, has mobilized personnel, equipment and materials to our former Tannery site to construct the groundwater remediation system per the EGLE-approved Response Activity Plan.

On June 12, Sevenson’s trenching subcontractor, DeWind from Zeeland, Michigan mobilized and began installing groundwater interceptor trenches. Two trenches were completed on the north side of Rum Creek before moving to the south side of Rum Creek. The trench installation is ahead of schedule and will be completed this week.

After trenching is complete, Sevenson will mobilize their equipment to start installing the outfall to the Rogue River which will serve as the outlet termination point of the groundwater remediation system. This work may be begin as early as this week, and will proceed throughout July.

We still anticipate work this year will continue through November.

Parking and Trail Detour Update

On June 18, following the Start of Summer Celebration, trenching began in the parking lot at the southern end of the property and a portion of it is now fenced off on weekdays for safety.  The parking lot will be fully open on weekends to accommodate increased demand and the Farmers’ Market, and access to the boat ramp will be maintained throughout the project except for during short time periods to allow for installation of a well.

As a reminder, the White Pine Trail has been temporarily re-routed during this duration of this project, and is anticipated to be reopened in October.

Air Monitoring Update

We continue to conduct air monitoring at the perimeter of the project site, and there have been no exceedances of action levels to date.  The air monitoring data is available in the “Documents” section of this blog or by clicking on this link.  We continue to evaluate the data to be proactive with dust control as needed. 

Site Photos

Photos of the site showing the grading and site preparation are below:

Aerial view from overhead drone taken of the installation of the first groundwater interceptor trench on the north side of Rum Creek.

Aerial view from overhead drone taken of the trenching activity on the south side of Rum Creek.

We will continue to use this blog to keep the community informed as our remediation work continues in the weeks and months ahead.  As always, residents with questions or feedback are encouraged to contact Wolverine Worldwide directly at HouseStreet@wwwinc.com or (616) 866-5627.

Tannery Remediation Update – June 7, 2024

On May 20, 2024, Wolverine’s lead contractor, Sevenson Environmental Services started to mobilize personnel, equipment and materials to our former Tannery site to construct a groundwater remediation system in accordance with the EGLE-approved Response Activity Plan.

Since then, Sevenson has installed perimeter fencing, soil erosion and sedimentation control measures, and constructed equipment staging pads and construction entrances from Main Street onto the property.

In addition, on May 28, fencing and detour signs were installed across the portion of the White Pine Trail that runs through the property, and this detour will continue while construction is underway.

Next, Sevenson’s trenching subcontractor, DeWind from Zeeland, Michigan will be mobilizing its equipment to start installing the groundwater interceptor trenches. This work may begin as early as the week of June 10, 2024.

We continue to conduct air monitoring at the perimeter of the project Site, and there have been no exceedances of action levels to date.  The air monitoring data is available in the “Documents” section of this blog or by clicking on this link, and it is updated every week.  We continue to evaluate the data to be proactive with dust control as needed. 

Photos of the site showing the grading and site preparation are below:

Aerial view of the former Tannery property from overhead drone taken on May 31st. The image shows the staging areas on both sides of Rum Creek.

Ground view of the soil erosion and sedimentation control measures being installed on the south side of Rum Creek

We still anticipate work this year will continue through November, with the White Pine Trail planned to re-open in October.

We will continue to use this blog to keep the community informed as our investigation and related work progresses in the weeks and months ahead.  As always, residents with questions or feedback are encouraged to contact Wolverine Worldwide directly at HouseStreet@wwwinc.com or (616) 866-5627.

House Street Remediation Update – June 7, 2024

We continue implementing the EGLE-approved work plan at our House Street property to construct three engineered caps over 27 acres as shown in the figure below and the approved plan.

Over the last two weeks our contractor, RECON, has continued to relocate and place material within the footprint of the caps.  Within the next two weeks they will complete final grading for the northwest cap, and by June 17 we anticipate that the geomembrane liner installers will arrive to begin placement of the liner over that graded mound.  Placement of the liner may require extended work hours on weekdays (7 AM to 7 PM), but should not result in any additional truck traffic outside of normal work hours. 

The installers will weld the seams of the liner together during placement using a heating tool.  Both RECON and GZA will collect samples of the liner welds to confirm that they meet the strength requirements before the liner is covered with barrier soil, topsoil, and seed.

Installation of the liner over the northwest cap is expected to continue through mid-July, and while that is happening RECON will continue preparing the other caps for liner placement so that the installers can move through each of them as they are ready. 

We continue to collect perimeter air monitoring on a regular basis, and there have been no exceedances of action levels.  The air monitoring data is available in the “Documents” section of this blog or by clicking on this link, and it is updated weekly.  We continue to evaluate the data to be proactive with dust control as needed. 

Photos of the site showing the grading and site preparation are below:

Aerial view of the House Street property from overhead drone taken on May 31st.  Southwest mound is visible in the lower left, northwest and northeast mounds with soil placement and grading in progress are located in the top left and right, respectively.

Aerial view of the northern mounds facing east.  Both mounds are in the process of being regraded to prepare for liner placement.

We still anticipate that grading, liner installation, liner cover, and related work will continue through November and that some remaining work, including grass planting, will occur in 2025. 

Wolverine will be using this blog to keep the community informed as work progresses in the weeks and months ahead.  In addition, residents with questions are encouraged to contact Wolverine directly at HouseStreet@wwwinc.com or (616) 866-5627.